Dear All,

Is there a way I can remove the "CHANGE NUMBER", above the "Key Date" from the routing screen (CR01)?

I was able to remove that from Cs01 (Bom creation) in OS27

Accepted Solutions (1)

Accepted Solutions (1)

former_member184655
Active Contributor
0 Kudos

Dear Rafik,

Goto T code > OP5A-> Double click on Field selection: Task list overview--->Double click on PP task

lists: initial screen--->Select the radio button for Hide for Change number.Save the datas.

Check in CA01 whether are you able to see the field Change number or not.

Now you will not be able to see this field.

Check and revert back.

Regards

Mangalraj.S

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

As you said you can remove the Change number from the BOM intial screen using the Tcode : OS27.

Similarly you can make the change number filed as Input / Required / Display/ Hide / Highlight for the Routing screen using the Tcode : OP5A.

Goto OP5A and select the PP tasks lists : intial screen and press the Modifiable tab. System will take you to screen "Fields Selection : Modifiabel Fields, where you can make it display / hidden etc.

Hope this will help you.

regards

radhak mk

Former Member
0 Kudos

Rafik,

Follow path SPRO---- Production---- Basic Data---- Routing--- Control Data-- Define field selection----- Field selection : Task list overview or T code OP5A.

Double click on 'PP task lists: initial screen'.

In the next screen select 'Hide' against change number & save.

Check out & revert.

Hope this helps you.

SmanS

Former Member
0 Kudos

Rafik,

You mention CR01 and you mention 'routing screen'. These are not consistant.

For CA01, try transaction OP5A.

Regards,