Hello,

I need some inputs on below query

If I didn’t select the check box ‘Check without RLT’ then

  • 1.If I create a sales order today(15.08.2018) for part A where there is no stock system will take (Planned delivery time + GRT time) example 15.11.2018 as RLT and confirms the schedule lines.

  • 2.After rescheduling tomorrow(16.08.2018) for part A whether the system will change the RLT to next day as 16.11.2018, so the confirmation date will keep changing for that schedule line unless there is a Shipping notification/Stock.