Rework Processing Scenario

Former Member
0 Kudos
76

Dear Friend,

While i am creating a Rework production order I got error like

Scheduling parameters are not defined for production orders.Here I am using the t-code CO01.

Can u please help me...?

Regards,

-Sibi

Accepted Solutions (0)

Answers (2)

Answers (2)

vasudevap_pushpalas
Active Contributor
0 Kudos

Dear

To rework of order follow this steps

1. Create reference routing in CA11

2. Create a Rework of Order in Co07

3. Attach this reference routing group with task list 'S'

Then Execute

With Regards

Pushpalas

Former Member
0 Kudos

Hi,

While creating prod. order,system pick up data regarding scheduling parameters from OPU3,

pl. make setting into OPU3 for Rework prod. order type, you are using to create rework production order.

Pl. try & revert in case of any querry.

Devendra