on 2012 Jan 06 3:44 AM
Dear Friend,
While i am creating a Rework production order I got error like
Scheduling parameters are not defined for production orders.Here I am using the t-code CO01.
Can u please help me...?
Regards,
-Sibi
Request clarification before answering.
Dear
To rework of order follow this steps
1. Create reference routing in CA11
2. Create a Rework of Order in Co07
3. Attach this reference routing group with task list 'S'
Then Execute
With Regards
Pushpalas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
While creating prod. order,system pick up data regarding scheduling parameters from OPU3,
pl. make setting into OPU3 for Rework prod. order type, you are using to create rework production order.
Pl. try & revert in case of any querry.
Devendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
39 | |
8 | |
4 | |
3 | |
3 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.