Hi Viktoriia,
You can show what is in your CJI8 report to understand the full history.
In CJ30 you need to delete your budget distribution from the lowest levels (3,4,5), next the AVAC will work with lowest available amount that will be from level 2: 50K.
Thank you,
Paulo