Hi, Gurus

How can I return budget from WBS-element? I return unused budget on a WBS element to the top level WBS element in the project thereby increasing the distributed

a

mount in the project but when I see CJ30 the budget is still there but without distribution amount

View Entire Topic
Paulo_Vitoriano
Active Contributor

Hi Viktoriia,

You can show what is in your CJI8 report to understand the full history.

In CJ30 you need to delete your budget distribution from the lowest levels (3,4,5), next the AVAC will work with lowest available amount that will be from level 2: 50K.

Thank you,

Paulo

0 Kudos

Hi!

I can't delete it because it shows the error massage.

I thought that I can delete it by using CJ38

Paulo_Vitoriano
Active Contributor
0 Kudos

1. Вы убрали распределение на 2020 год, а что за картина по общему бюджету? В том же отчете по отдельным позициям есть галка показать данные по суммарному бюджету. Возможно он у вас также распределен.

2. Что у вас стоит в профиле бюджета, контроль годовой или общий?

Paulo_Vitoriano
Active Contributor
0 Kudos

You cannot remove those 10K, because they have been removed already, just look at the Current budget column (that is different from the Original budget). Check your total budget distribution, as that is likely to contain same 10K at lower levels.