Restrict all goods movements for materials untill the latest costing run ex

Former Member
0 Kudos

Hi dudes,

1 here i have a requirement that i need to restrict all goods movements in the month for all materials(SFG,FG) untill the latest costing run(standard cost estimate) on 1st of each month.

2. Can we restrict the status of process order in such a way that Conformation can be done only after the goods issues against production order. The goods receipt can be done only after the conformation of the process order.

Thanks in advance.

Robert.

Accepted Solutions (1)

Accepted Solutions (1)

former_member196398
Active Contributor
0 Kudos

Robert,

Procedurally you can block, by not opening the current period, before the costing run is completed, just when you wanted to release the cost estimate, at that time you can lock all users and then open the next period and then release your cost estimate and then unlock all the users. You need to work with your Basis/MM/FICO guys to have this procedure implemented.

On the GI Check before confirmation and Confirmation check before GR, you can use Confirmation and GR releated User exits to check. There are many posts on this topic, a simple search on this forum would take you to the thread.

Regards,

Prasobh

Former Member
0 Kudos

Thank you Prasobh..