Hi,

Pls let me know the differences between using transactions ME57 and ME58 for creating a PO.

Thanks.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

ME 57 is for PR's to which vendor is not assigned. You have assign the vendor first and then process the PR.

ME58 is for PR's already with vendor and can be processed directly.