Hello Everyone,
My client has one requirement- They want to hit the release strategy in PO for Net Overall Value along with the Item value too.
Just for example-
So is this possible to achieve?
Regards,
Siddhesh Ghag.
Hi Siddhesh ,
As you may already know, the standard PO workflow condition only contains the overall net value. Therefore, your requirement may not be achievable with the standard setup. You may want to check on enhancements for your requirement.
To implement your custom logic for the conditions, you may want to explore the available extensibility options for the PO workflow process. Please refer to this link for information on the available BAdIs in S4 Hana Cloud for custom conditions.
Regards,
EIP
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
114 | |
8 | |
6 | |
6 | |
6 | |
5 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.