Requirement Qty in Report MCRE(Based on S026 Info Structure)

Former Member
0 Kudos

Hi, PP gurus

Issue:

When i run report MCRE for material usage wrt Prod.order selection as input.

Requirement qty as per BOM component explosion is not updating correct figure.

suppose say my BOM comp. reqd qty 100 it is showing there in MCRE as 200.(Exactly 2 tim

again i have restricted user from not changing component qty in order.

Actual withdrawn qty showing that is correct but reqmt qty are not updating in S026/MCRE.

Suggestion and Solution required.

Rgds,

Yogesh Thorat.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear Yogesh,

1) is it happening only one material or any other materials showing same way

2) if only for one material then unplanned Goods issues might be done

3) simultanously compare the reports COOIS & MCRE

Regards

Madhu

Former Member
0 Kudos

Hi,

There are no unplanned issues for that material.

Still the prblm exists.

Rgds,

Yogesh

Former Member
0 Kudos

Dear Yogesh,

As per ur post it is clear that only for this material problem is

Now from here it is tough to judge

As i said earlier, Just check in COOIS, MB51 & MCRE

Also check for that particular prdocution Component view for the Qty

You should able to Figure it out

Good Luck !!!!

Regards

Madhu

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi ;

SPRO: Logistics Information System (LIS) =>Updating=>Updating Control=>Settings: Production=>Activate Update and Release Version for each Order Type

For production order type in plant check whether Update is activated or not. Also check other parametrs in Updatinf : Shop floor control :INFO Structure ( T code : OMOD)

Regards,

Sanjay