Hi Gurus,

I am required to add the output values of MD04 in one of my report. But in which tables will i get those values... Or is thr any other way i can get those values...

Please guide me..

Regards,

Accepted Solutions (1)

Accepted Solutions (1)

pankaj_singh9
Active Contributor
0 Kudos

Hi,

Details in MD04 doesn't come form a single table. it comes from many tables and it is very difficult to have exactly the same details in any other report since the status of report MD04 keeps on changing as per the daily transactions and stock situation of the material. It is not just picking data from a table, it also involves lots of calculation to be done.

Former Member
0 Kudos

Hi Pankaj,

I need data of the column Planned independent requirements.

Any guidance in this way??

What best can we do to get those values... Please throw some light on this..

Regards

pankaj_singh9
Active Contributor
0 Kudos

For PIR data, check in table PBIM - Independent Requirements for Material

Former Member
0 Kudos

hi,

I cheched that..i am not able to find the values...

I chkd PBED,PBIM, PBID as all r interconnected...

Regards,

pankaj_singh9
Active Contributor
0 Kudos

Yes, all these tables in a combined way will solve your purpose.

Answers (1)

Answers (1)

Former Member
0 Kudos

You will get those values from structure MDEZ.