Dear Guru's,

We need report as given below but could not find in Standard reports. Please suggest if any available.

Material code Material description ROL level UOM Stock in hand PR pending PO pending

X material Creap Paper 300 KG 100 100 4520202020

please help.

Regards,

SAP CONS

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

thanks

pankaj_singh9
Active Contributor
0 Kudos

Hi,

You can use report CO03 - Plant Availability. Here Change the layout and add 'Reorder Point" column and other required details.

But this report can be viewed for single material at a time.

Based on the logic of this report, you can develop a report with help of ABAP.

Former Member
0 Kudos

Dear Pankaj,

CO03 is for production order dispaly. How we can view the availability? By clicking on 'Material availability' check. Please let me know if I am wrong.

Regards,

SAP CONS