Dear All

We have value stuck in Rem Ord Plan in budget.

I understand the calculation that

Rem Ord Plan = Plan(In network) - [ Commitment + Actual]

In our case

80 = 200 - [20 + 100]

Means we have planned for 200 but we have negotiated and brought the cost down to 100.

My query is

How to release this amount from the Rem Ord plan ( network).

We cannot close the network since some commitment are yet to be delivered by the vendor.

Also if we do Final confirmation of network line item with CN25, will the amount be available??

Regards

Iyer Kartik

Accepted Solutions (0)

Answers (1)

Answers (1)

sanjeevc
Active Contributor
0 Kudos

How to release this amount from the Rem Ord plan ( network).

Either to less plan or fully CNF

We cannot close the network since some commitment are yet to be delivered by the vendor.

yes you can not close the network second way if you do teco to that activity then commitment would be nullified


Also if we do Final confirmation of network line item with CN25, will the amount be available??

Amount would not be available in cn25 screen.

Regards,

Sanjeev