on 2013 Apr 17 9:58 AM
Dear All
We have value stuck in Rem Ord Plan in budget.
I understand the calculation that
Rem Ord Plan = Plan(In network) - [ Commitment + Actual]
In our case
80 = 200 - [20 + 100]
Means we have planned for 200 but we have negotiated and brought the cost down to 100.
My query is
How to release this amount from the Rem Ord plan ( network).
We cannot close the network since some commitment are yet to be delivered by the vendor.
Also if we do Final confirmation of network line item with CN25, will the amount be available??
Regards
Iyer Kartik
How to release this amount from the Rem Ord plan ( network).
Either to less plan or fully CNF
We cannot close the network since some commitment are yet to be delivered by the vendor.
yes you can not close the network second way if you do teco to that activity then commitment would be nullified
Also if we do Final confirmation of network line item with CN25, will the amount be available??
Amount would not be available in cn25 screen.
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
10 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.