Hello Team
We are able to release the production order without costing run the other material types system prompt error message to have a costing run.
we wants order only get release when cost estimate have been taken.
Br, Kiran
Hi,
plenty of solutions are available on click of search.
BTW this can be achieved through user status as well as through enhancement in production order while saving.
Logic-
Check EXIT – PPCO007
For order material and plant check costing date entries in Table KEKO and if order creation dates falls under costing dates then allow system to create order otherwise through an error “ Please run standard cost estimation”
Costing Dates
Table KEKO
Costing From date – KEKO_KADAT
Costing TO date- KEKO_BIDAT
let me know, if you require source code
Regards'
Riyaz
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
8 | |
7 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.