Hi All,

Any one can please let me know how the configuration and testing will be done for release strategy in MM?

Thanks in advance,

cheers,

Kumar

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Answers (4)

Answers (4)

Former Member
0 Kudos

thanks both of you

Former Member
0 Kudos

hi

after assigning the values simulate the release strategy.

Please use the T.code for create Characterstics :CT04

Create class T.code : CL20N ( Class type 32)

For PO using the Table in CEKKO and For PR CEBAN

Please try the using the above information ,if need any help please revert back.

With regards

Former Member
0 Kudos

HI Kumar

1 . Define Characteristics of each control paramaters ( Whatever we need to control Eg. value , Purchase group, material Group)

2. Define the Class and assign to the Characterstics

3. Define the Release Group and assinge the Class

4. Release Indicator (B: Blocked R: Released)

5 Define Release code Release code for the approvers)

6. Define the Release Strageies

A. Enter the Release code (Who is the approver) for the particular release strategy

B. Maintaing the Release status codes as per the approves release code

c. Classification : Enter the charactersitic and assign the values.

Former Member
0 Kudos

HI,

Check out the below link.

[http://www.sap-img.com/materials/release-procedure-for-purchase-requisitions.htm]

You can do the testing of Release Strategy by creating a single PR/PO & by changing the different parameters such as PO value, Purchase group, Plant, P.Org etc & Check whether system is determining different releases for your PO based on the configuration.

Thanks & Regards,