on 2019 Apr 26 6:33 PM
Hello!
I have to modify different Release Strategies for purchase requisitions (PR) due to the client needs that a Manager can approve a PR regardless the first approval is not done
Example:
-Release codes:
C3 Purchaser
GT Manager
C3 Purchaser -> Release possible
GT Manager -> Release prerequisite missing
Final release = C3 + GT (here both approve to unlock the PR)
But I also want that the final release could be do it just for GT. That will be:
Final release = C3 + GT and/or GT
Is it possible?
Regards
Hello Sofia,
Maybe you can try to achieve this by not setting any release pre requisites in the settings of the release strategy
As is:
Code/Release prerequisite
01 02
01 - [ ]
02 [x] -
To be:
Code/Release prerequisite
01 02
01 - [ ]
02 [ ] -
and with regards to releases you can specify which release codes can release the document:
I hope this helps.
Best regards,
Oscar.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
9 | |
8 | |
6 | |
5 | |
5 | |
4 | |
4 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.