Release Indicator

former_member1283268
Participant
0 Kudos

Dear All

For my PR/PO release strategy we are having parallel release i.e if a PR/P is having release code A0, B0 and C0 , the said PR/PO can be directly released at B0 or CO. This can be done by removing release prerequisite in release strategy. Currently we are using two release indicator A - Not released and C- Released. What is happening is that even if PR/PO is partially released the release indicator is A - Not Released . Now we want to have third release indicator C - Partially released. How do Iachieve this>>>>

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

Hi satish ,

You can try like.

In Release prerequisities A0,B0 & C0

Select tick mark at B0 in 2 line don't select the C0 2 tick mark

Ex. Below.

A0

B0 *

C0 *

Now you can get one more line in Release Statuses.

1 line : A

2 Line : A

3 line : B

4 line : B

5 Line : B

Now you check the process . It will work.

SAM

former_member1283268
Participant
0 Kudos

With parallel release this is not possible!!

Former Member
0 Kudos

what do you mean by partially released?

former_member1283268
Participant
0 Kudos

Partially released means if PO is having release codes A0, B0 and C0 and it is released for A0 and B0 only .

Former Member
0 Kudos

Hi Satish,

You have to achieve this using release status tab in release strategy for PR/PO.

And you need to assign your characteristics in classification as well for that release strategy.

Hope this will help.

Regards,

nitin

Former Member
0 Kudos

HI,

release strategy for PR and PO is different. you can not combine the both.

create new release indicator and induce it in release stratergy as prerquiste.

For PR there are 2 release procedures. go for "Release procedure with classificaton"

Path for release procedures

SPRO: MM> purchasing > purchase order > Release procedure for Purchase orders

SPRO: MM > Purchasing > purchase requistion > Release procedure > Procedure with classification

former_member1283268
Participant
0 Kudos

If my release strategy is having release prequisite then it is possible to have release indicator B - Partially Released, but I am asking without release prerequisite is it possible to have indicator B.

Former Member
0 Kudos

Maintain new release srategy as you did earlier for two release indicators.

Now you are going to use three release indicators.

It can possible

former_member1283268
Participant
0 Kudos

???