cancel
Showing results for 
Search instead for 
Did you mean: 

Release Date in CK40N Year end

former_member218253
Active Participant
0 Kudos
522

Hi Team,

The server time is in GMT and CK40N does not let me release costs till the server time is 12:00 AM next year. This delays good issues in countries that are already in the new year. Is there any workaround for this ( other than waiting till the server time is 12:00 Am next year?

Any help will greatly appreciated.

View Entire Topic
former_member402435
Discoverer
0 Kudos

The process is as follows, when standards are released in many countries. There should be no accounting movements in SAP until approximately 8.hours the following day (in fact the system blocks all users, (excepted those user, that release with CK40N).

One of the issues that can occur is that if a country runs CK40N, blocks the transaction for other users in other countries and cannot run, until you stop using it.

Plants continue with their production processes but without registering in SAP to avoid inconsistencies, once the process is finished in all countries, load the data in SAP.

Use contingency plan for operation without system. And End year close process with strict calendar.

Regards