HI Gurus

In a Make to Order scenario based on sales order say the customer wants it immediatly to go into production

It needs to set priority for that corresponding production order how to do that

Thanks in advance

Rajesh

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Thanks for the Inputs

Self answered

It has been automated, value comes from sales order directly to proudction order

Rajesh

Former Member
0 Kudos

Hi Rajesh,

Please let me know how do you automated?

Regards,

Sudhakar.

Former Member
0 Kudos

HI Thanks for the Info

I have checked in the production order priority in help they have given that priority from sales order will be fetched in case of assembly order

i am using strategy group 70 in material master

but i am not getting

how to do that

Thanks in advance

Rajesh

Former Member
0 Kudos

Thank u Sir

I have checked in sales order and set the priority as 1 but it is not automatically fetching in the

corresponding production order as per the priorty how to do that

Thanks in advance

Rajesh

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

It will not come to production order you need to set it manually in production.

Go to CO02 production order set the priority of that particular production order like 1,2,3,4. Its a standard SAP practice. This order will execute as per priority field.

Hope clear to you.

Regards,

R.Brahmankar

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Go to CO02 production order at bottom of first screen you will get the priority field

You can assign the priority of that particular order like 1,2,3,4.

Or for sales order go to the SO, choose the item, in the menu>edit>fast change of-->priority, in the pop-up assign a value of 1.

Hope it will help you.

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi Rupesh,

Could you please explain more how I can set priority in CO02. Which bottom that I should hit for setting the priority?

Below I upload the CO02 screen.