Regarding Marking of cost estimate

Former Member
0 Kudos

Hi Experts,

Kindly provide the solution for the below points.

*We only select the 1 material, why in the Marking section system show 6 materials been marked?

*Does the material fail for mark or successfully?

*How can we check the result and who can help us release the block status?

*How can we give the material a new std cost? Should we need to run it again?

Thanks a lot in advance,

Satish.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Satish,,

Accepted with the above answer, Please check the Bill of Material Once.

Correct me if I am wrong...

Thank you......

Former Member
0 Kudos

hi satish,

i hope you are doing cost estimate for finished product it may contain some other materil like SFG, raw material, packing material.

you have selected with quanity strucute structure for both raw material and packing material also.

so the cost estimate is been performed for both both type of material.

check it once in bom how many materials available for it.

thanks

kareem

Former Member
0 Kudos

Hi Team,

Thanks for you info,

i have cheked in KEKO table and found the 6 material related to cost run is any relation wiith my issue.

kindly advice.

Thanks a lot again.

Regards,

Satish.

Former Member
0 Kudos

hi satish,

Please check in CS03 what are the materials available in it.

if u find same material in that table or the costing run.

it is correct as per my assumption.

thanks