Hi

How to get the dependendent requiment to get converted in purchase requisition on doing MRP run for the finished good.

Regards,

vivek

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

In MRP purchase requisitions will automatically be created if dependent requirement exists if you put 1 in the create purchase requisition indicator in the MRP run screen

Former Member
0 Kudos

Hi Vivek,

In customizing Tcode: OPPQ. maintain the data for your plant.

Regards

TRin