on 2020 Oct 03 7:07 AM
Hi All
Problem: While I am doing the Cancel GRN (MIGO) I am getting the below error
Deficit of BA Unrestr. prev. 3 EA: Material (CHCP0000496) Plant (CP01) Storage Loc (MG02) Batch (NA)
Message no. M7021
But I checked the stock in MMBE stock is available
MM03
NOTE: This Doc posting date was 24.09.2020 (last month) and you are trying to cancel on 10.03.2020 (This month) but previous posting allowed indicator enabled.
MMRV
Please help me
thanks ,
Please check with respect to which PO the current stock in MMBE is reflecting , if it is the same PO for which you earlier did MIGO.
Also check if there were any material movements/Goods issue performed for this material from CHCP0000496) Plant (CP01) Storage Loc (MG02) Batch (NA) in previous period.This might be one of reason for which it is showing 0(zero) quantity for previous period in Unrestricted use.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
115 | |
9 | |
8 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.