Hi

Its allowing to create PR,PO and Service order,With out  entering the budget in cj30.not displaying any error message.i configure the tolerance limit for budget.But if budget is allocated then its working proper with budget control.

How to control if the budget is not allotted.it should give an error msg "budget is not allotted"?

Thanks in advance

View Entire Topic
0 Kudos

Hi,

You may use the following options

Option 1 - Make use of User Status. By creating a user status, which does allow to budget but not to book any cost or committment.

Option 2 - Execute the program and activate availability control. This can be done by CJBV.

Hope this will help.

Regards,Ravi