Dear Friends What is reduction strategy in routing & what setting it requires

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

If the lead time of the order is longer than basic dates, then system applies reduction strategy.

The system reduces the lead time of the order step by step and checks after every reduction whether the dates calculated lie within the basic dates.

System try to eqaul the basic dates and lead time date by reducing float before and after production time in scheduling margin key as per the reduction level maintained in configuration.

Settings:

Shop Floor Control, Operations ® Scheduling ® Define Production Order Scheduling rameters