Recursive BOM

former_member267531
Participant
0 Kudos
250

Hello Team

We are having one scenario that we wants to have a no procurement proposal at component Level but needs at header level & the material is recursive so how can be achieved in Recursive BOM scenario ?

Br, Kiran

View Entire Topic
Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Whenever you are working with recursive BOMs, I suggest you to use a storage location MRP Area for the component, otherwise, you might end up with incorrect results in MRP. If you don't want to have any replenishment proposal created for the component, just set MRP type ND on the MRP Area.


Regards,
Caetano

former_member267531
Participant
0 Kudos

Thanks Caetano

I will try out this mentioned setting.

Br, Kiran