Record of PIRs

Former Member
0 Kudos
124

Dear All

i am starting my production plan by entering direct PIRs in MD 61 and usin strategy as Gross requirement Planning.

Now i want to make ABAP report Plan Vs actual production.So i have to pick the plan PIR Quantity from MD61 screen.But after some time some of the PIR consumes so from where can i get my plan qty.If any confusion in understanding then please reveret back.

View Entire Topic
rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Go to table PBIM for given material / plant etc combinations

From this table note down "Reqms Pointer"

Use this pointer in table PBHI and u wil entire history.

Regards,

R.Brahmankar

Former Member
0 Kudos

Dear Bharmarkar

Thanx.

I have entered PIR on weekly basis

i meen W1 W2 W3 W4

100 200 300 400

At this time i have record. but after a 2 months i want to run abap report weekly Plan vs weekly production so from where can i have that record weekly

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Yes you can fetch the value from these table also in MD73 you will get the PIR with history requirement.

Regards,

R.Brahmankar