Re evaluation of Absences and Quotas.

Former Member
0 Kudos

Hi All,

Our Client have Sap with Timemanagement and Quotas are received from Legacy SAP.

As we receive the Quotas,Attendances,Substitutions from Legacy Infotypes.We have Planned to Scedule the program.

RPTUPD00 and RPTBPC10.

Can you Please suggest the Variants i mean the input values for the fields below.

RPTUPD00

Dates/Period:

Reevaluate Absences:

Company Code:

RPTBPC10.

Dates/Period:

Correct Leave Deduction

Correct Absence Quota

Company Code:

Considering performance what should be inputs for these.

For RPTUPD00 we using another program to start the batchinput session automatically.

Once this program is comepleted after 4hrs we are scehduling the program RPTBPC10.

Any suggestions how you guys handle the Re evaluation of Absences and Quotas.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Execute the reports till today for all the personnel numbers.

That will bethe ideal way to do it.