on 2010 Jan 02 7:22 AM
Dear Experts,
We are trying to create a project from sales order ,we need to create One WBS per each Item. But when we set SD/PS assignment indicator in standard project definition, system is throwing the following error.
"SD/PS Assignment" indicator cannot be set Message no. CJ119
My Standard Structure
M2-000004
M2-000004.01
M2-000004.01.01
M2-000004.01.02
M2-000004.01.03
M2-000004.01.04
M2-000004.01.05
M2-000004.01.06
M2-000004.01.07
M2-000004.01.08
Please help me.
thanks
Shareeq
remove the one root only radio button option from your project profile and then check
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This means that your basic settings for assembly processing are not correctly set up.
Read SAP help or more and also check forum for more information.
Basically you need to ensure -
You have to set up std network and std WBS as templates
material with sales view
assignment between material and std network - txn CN08
Configure requiremetns that allows assembly in sales order - ie to generate network
Once these are done then you can use the SD/PS assignment indicator in the project definition
For this the only other mandatory requirement is that in the project profile the only one root indicator should not be set.
Any experienced PS consultant should be able to set this up for you.
Dear Virendra,
Keep up your good work. My problem is solved now. May God Give you a prosperous and Happy Life.
The Standard WBS should be created with the Edit Mask as the operative project.
I have created a Standard WBS without the edit Mask ( SPRO - OPSJ).
Thanks again for your help.
Regards,
shareeq