Hello experts,

we are verifying a scenario where a plant is "abroad".

Example:

Company Code = A (country = DE)

plant 1000 (country = DE) belonging to company code = A

"new" plant 2000 (country = CZ) belonging to company code = A

SAP says that my plant 2000 must not be "real operation center". Therefore my question: is proper product planning (and execution) possible in such plants ? .. or what is meant by "real operation center". What are the restrictions or what forces the need in SAP to place plant 2000 into separate company code in country CZ.

Regards

Thomas

View Entire Topic
Former Member
0 Kudos

hi,

You can use subcontracting procedure with BOM and separate pricing procedure for 2000 plant treating it as vendor. Check constraints for statutory documents print for sending and receiving the materials.