Dear Fds,

While operation confirmation when i insert shift, i m getting the warning msg "Execution period does not lie completely within the shift " how to remove this?

Thanks in advance

Nishj

Accepted Solutions (0)

Answers (1)

Answers (1)

krishna_chandra5
Active Contributor
0 Kudos

Hi Nishj,

My suggestion is in OPK4, second tab 'Individual entry general', in shift proposal select current shift, so that the system will automatically take the shift and no need of manually giving that. In this case i think you will not face the error.

Have you have already decided to give the shift manually, please check and revert back.

As per my knowledge in operation wise confirmation shift will not be displayed in standard SAP. Please let me know if you are using any exit.

Regards,

Krishna Chandra

Former Member
0 Kudos

Dear Krishna,

I can not set it as current shift, as are confirming A shift's operation in B shift. Also,What else we can do. I have activated business function to activate the shift field in co11n