"Due period in days" one more field needed!

Former Member
0 Kudos
96

kindly look in to the attached Screen Shot (available buckets for Debtors Ageing Report)

Actually we have to add one more bucket in to it as 15 days….!

Please let me know how this can be done.

Can i add one more field for the "due period in days" one more field?

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

Hello Aneesh,

This is a standard report and hence, you cannot add another field for Due period in days.

Alternatively you can add field, Proposed Posting Date to meet your requirement.

Open the report>Add Fields>Dimension: Trade Receivables Payables>Proposed Posting Date>Year Week

Select the check box for Display in Report and Display in Selection Area to show the field in the report.

You can select required two weeks of any month to view the data with in 15 days.

Regards,

Annapurna

Answers (1)

Answers (1)

harsh_p9
Active Participant
0 Kudos

As of now there is no extra field - Due Period in days. In the default display, the period structure is as follows: 30 days (period 1), 60 days (period 2), 90 days (period 3), 120 days (period 4).

However, these values can be changed.

Regards,

Harsh Patel