question on MD04 option

former_member323340
Participant
0 Kudos

Hi All,

Can anyone tell me the use of the 'Display at Goods Receipt Day' option available below to the stock requirement list within the MD04 transaction.

regards

shyam

View Entire Topic
rammohan_shenoy
Active Contributor
0 Kudos

shyamsundarl

This is useful when you have Goods receipt processing time in your material master ( refer MRP 2 view) .

so for eg. Material delivery time =10 days, GR time =2 days. By defualt MD04 will show material available time =12 days

Incase you wish to see when the material would actually arrive you use 'Display at Goods Receipt Day' option & MD04 will then show 10 days.

So on Md04, PO shows avail time = 29th July 2010. If you select GR date it will display PO at 27th July ( assuming 2 days GR time)

I am sure this explains the concept. More question splease come back.

thanks,

Ram