Dear experts,                                                                                                                                                                                                                 I have a doubt in flexible planning, i have created a info structure with 2 aggregate information in my planning type "Planned value" and "Actual value". In MC94 i have updated the requirement qty for the material for "Planned value" as 300 ea. When i transfer the demand in MC90, the requirement qty is displayed as 150 Ea. I am unable why the requirement qty of 300 ea is getting changed to 150 Ea. How this value is of 150 Ea is calculated

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Existing withdrawal quantities are subtracted from the total. Se note belos for details:

http://service.sap.com/sap/support/notes/793258

BR

caetano

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

In addition, modification note 144513 may be helpful.