Hi Gurus,

How would i see the quantity in cost report in process order. For e.g. if there is an activity in the operation list and there is no cost associated with this activity, but there is a quantity associated with it. I want to see the quantity in the report. Is it possible to get this quantity.

Thanks a lot in advance.

Accepted Solutions (1)

Accepted Solutions (1)

former_member188826
Active Contributor
0 Kudos

You can see it in COR3, Goto> Costs>Analysis. The standard layout would show the $ and the quantity for planned and actual. The operation must have been selected for costing relevancy.

Answers (0)