on 2008 Jan 05 8:37 AM
Dear PP GURU/Rajesha,
Inspection lot is generated after production order is released,
then what would be the next steps to put stock in unres. use.
Pl give all t.c.
Regards,
Basant
hi
U can post ur stock into unrestricted by t code QA11, by clearing the inspection via usage decision.
Regards
Rajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
i am using INS TYPE- 04, in qa11 when i am trying to post the stock the system is giving following error
You cannot make a quantity transfer posting for insp. lot 030000000012
Message no. QA068
Diagnosis
You cannot make a quantity transfer posting for inspection lot 030000000012 because the lot does not have any stock "in quality inspection", or because the inspection lot stock has already been completely credited (posted).
what is the solution for this pl tell me?
Vikas
I think it is connected with the one of yoyr thread.
You need to perform RR, confirm the operation and GR.
In which stage you want notification and rework order?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
105 | |
8 | |
6 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.