PURCHASING BOM:::::::URGENT

Former Member
0 Kudos
73

Can we maintain Purchasing BOM's ?

Accepted Solutions (0)

Answers (2)

Answers (2)

BijayKumarBarik
Active Contributor
0 Kudos

Hi,

You can use BOM in Purchasing Side for Sub Contract Process. Material is sent to subcontractor as components and he processed it and send back to as finished product. So for material (Finished Goods) that can be procured externally, and you have to maintained BOM (CS01) with components (Raw Materials){{{ make a transfer posting to issue components for SC PO(In ME2O directly or by MB1B with 541 Movement type}}. Any waste generated and received during subcontracting process can be maintained as component with negative quantity in the BOM.

So BOM can be used for Production or engineering or costing or Sales or plant maintenance .Use t.code: CS01 and create BOM by entering Material , Plant and BOM usages for like example Production or Sales or plant maintenance. Here you must take care about creation date and valid from date. In the next screen, you can enter components details like item cat and quantities required. Now select component item and click Item or press F7, now in this screen you can enter scarp in % basis in basic data tab and is it vendor material or customer material in status /Long Text tab in material provision indicator, in Administration, you can also maintain the valid from & to date. You can explode the BOM in t.code:CS11

You can use the BOM in subcontract PO during subcontract PO creation & explode the component details (before that you have supply component to Vendor in 541 movement type with MB1B or use t.codeME2O.

Regards,

Biju K

Former Member
0 Kudos

Hi,

These is No BOM called Purchasing BOM.

In SAP it is production BOM...IT can can be used in 2 menthods.

1. Internal - for production orders ..If headed material is In house manufacturing Part.

2. External - For Sub contract Purchanging use. - In material master you have maintain procurement type F in MRP

If material can produced inhouse and sub con - user procurement type X in Material master.

Thanks,

Kumar Arcot

Former Member
0 Kudos

Hi

No we cannot maintain, Purchasing BOM.