hi

there is a sub DC where replenishment takes place from a bigger DC only when safety stock goes down.

now when the safety stock goes down say today, MRP generates PR which has delivery date as today and with a release date in past based on planned delivery time, GR time etc.

but in real sense, it would be apt if system tells the delivery date in future considering the lead times and release date as today..

can it be attained by fwd scheduling ? if so how do i do for selective plants.

Pls suggest.

regards

joe

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Is this sub DC defined as a plant in SAP ?

Which is the MRP type for the items (consumption: i.e. PD or somethig or reorder point as V1 ).

There is some kind of demand on sub DC so you can foresee this problem ?

without demand on the items, the system will react "later" when the SS is reached.

Whenever a demand exist, the MRP will prepare the supply element in advance....

Perhaps, if the consumption in unplanned, you should shift to a V1 MRP type , with a reorder point.

Answers (1)

Answers (1)

Former Member
0 Kudos

This will happen if the requirement is either PIR / Dependent requirements.

Since safety stock is a kind of compulsory requirement it will show imediate date with a error.