Purchase requisition created in discontinued material after MRP run

nidhi123
Explorer
0 Kudos

Hello Guru's,

I have a material which is set G3 status (Discontinued) in Material master MRP views, but still system generating the Purchase requisition and dependent requirement after MRP run.

it is a phase out code we will not produce it. 

please help me to resolve the issue.

nidhi123_0-1716530433318.png

below u can see the details for G3

nidhi123_0-1716540480536.png

 

thank you in advance

View Entire Topic
matjazmoser
Participant
0 Kudos

Greetings,

you can try setting MRP type to ND at material master MRP 1 tab.

matjazmoser_0-1716872775458.png

Best regards!

 

nidhi123
Explorer
0 Kudos
it is already in ND MRP type
matjazmoser
Participant
0 Kudos
in that case you can try deleting the purchase requisition item for the material in question and then run the MRP