Hello,

A planned order in MD04 was converted to PR and PR to scheduling agreement .

But what i find that the planned order is still existing in MD04. Why this has happened.

Also is there any way where i can find which PR was converted to which SA.i.e link between pr and SA.

When a planned order is converted to production order , the prod. order has the no of planned order.

Is there any wy / table to find similar thing for sched. agreement

Regards

Shankar R

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi there,

Check EBAN-EBELN

This is the field feilled by follow-on PO so I'd assume an SA would be the same

Hope this helps,

Regards,

Matthew

Former Member
0 Kudos

Hi Matthew,

Thanks for quick reply.

Table EBAN is indeed helpful. I would also like to know , if there is any table for purchase requistion where i can find from which planned order it is created.

Regards

Shankar R

Former Member
0 Kudos

Hi ,

I rephrase my question a mistake in quaestion raised.

The pur requistion is used to convert it to an SAgreement.

But in MD04 , I see both the pur.req as well as scheduling agreement .

I guess only SA should be seen .

Regards

Shankar R