Dera ALL,

We have two requirements:

1.On PO print we want the rates per unit on Printout.

2.After saving the scheduling agreement , there should be provison to change the Scheduling Agreement once it is saved.

Best Regards,

Venu

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

fro 1st req.:

Make the message with per unit price and then generate the spool in ME9F for temporary time. in mean time make the changes in your SMART form call the struc with filed MEPO1211-MENGE & display the same item wise.

for 2nd req:

what thing you want to change?? for schedule line change you can do it by ME38. and many other thing are there please tell bit specifically

Regrds

S

Former Member
0 Kudos

Thanks for replying,

I want to know once the Schedule line is created and is released . If after releasing it if i want to change it can i change it?

What would be its effect on relase strategy.

Will it be again triggered?

Best Regards,

Bhasker

Answers (1)

Answers (1)

former_member335885
Active Contributor
0 Kudos

Hi,

Ask the abaper to incorporate this MEPO1211 - NETPR table and field name in one of the columns in the PO print out.

You can change the scheduling agreement in ME32L and delivery schedukles can be changed by ME38.

Thanks & regards,

Kiran