PS validation settlement rule before release project

Mahrenholtz
Newcomer
0 Kudos
175

Hello, we are searching for a solution regarding settlement rules in PS.

We want to validate if there is maintained a settlementrule in al WBS element before the project is released.

We have S4HANA ON PREMISE 2020 02 (05/2021) FP.

 

Regrads

 

Sebastian

View Entire Topic
Paulo_Vitoriano
Active Contributor
0 Kudos

Hi Sebastian,

The classic solution would be a default user status that prevents Release, but is automatically removed upon Settlement rules status. 
If you use AuC with IM it can get a bit more complicated as rules are generated upon Release, but not showing SETC.

Regards,

Paulo