Former Member
0 Kudos

can anyone give me the table for storing the project settlements and project charges ?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

PRPS and PROJ ...WBS related

BPEJ ...budget costs for WBS elements

check other tables COSP,COEP,COST for the costs

also check the fun module

K_CO_OBJECT_BALANCE_GET for getting the aCTUAL COSTS OF wbs ELEMENTS

Reward points for useful Answers

Regards

Anji