cancel
Showing results for 
Search instead for 
Did you mean: 

PS/Internal Activity:- Work Centre to have unit of Measure other than time

Former Member
0 Kudos

PS/Internal Activity:- Work Centre to have unit of Measure other than time say EA.

I wish to use EA as UOM in WCentre of Internal Act. When I put EA I get this message:-

"Enter a time unit, since you have entered either work or actual workIn wormk"

Current settings are in WC:-

Basic Data Tab:-W.C. Categ:- 0006,

Cap Categ- 001, other form -SAP008 and 002, SAP 008,

Scheduling TAb:-WOrk Dimension - No dim., and Work Unit- EA

In Capacity detail also I ahve given 700 units = 9 hr of work

Standard av. Cap = 08.00.00 to 17.00.00

Thanks

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

hi , please try leaving the "work Unit" feild as blank in the sehduling tab.

It worked for me.

Rgd

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

Hi,

In standard available capacity, try changing the unit of capacity to EA.

Regards

Former Member
0 Kudos

Dear shrikant,

we have already maintained the std. available capacity as Each.

We can see the std. avail. capacity as 100 EA = 9 HR.

But,when are you trying to calculate the work ,system shows error'Enter time unit' since u r entering work.

Former Member
0 Kudos

Dear Gurus,

Please tell me scenario of Activity(internal,extenal,cost,services ) abt how it is used and how it is used......

Former Member
0 Kudos

HI

Please look in to the help of SAP under the strucure node -->Acivities. this will calrify you,

Regards.

Varaprasad