Hi,

I am budgeting at WBS levels in project using CJ30. In the tolerance limits, I have given Usage 100% and action 2 u2013 Warning with mail to person responsible. I havenu2019t given Error anywhere.

But, Still while I am posting to the network below the WBS whose limit is reached to 100%, I am getting error message saying budget exceeded. Even, I tried to give WBS element, getting same error.

Error message number: BP604

Please let me know if I am missing something in configuration

Thanks in advance,

Satya

View Entire Topic
Former Member
0 Kudos

Check person responsible for said WBSE is given or not. If there is no person responsible for WBSE, warning message will be converted to error message.Also you check in OPS6 , in column office user you put User id.