Hello,
PRT functionality does not exist for process orders (i.e. PP-PI). I can see questions about this subject dating back many years.
Per note 350614, solution is to simply not use PRTs with process orders.
Can you suggest a work around for scenarios where you have a genuine production resource, for example, material which is re-used a certain number of times?
I find it hard to believe this requirement did not come up before for standard PP PI to handle.
I am developing a process to create an equipment PRT and record measurement points against it in order to count number of times PRT has been used. This will be a manual work around. I feel good about it, but, as you know, this is PM functionality, not PP.
Can you share thoughts / approaches you took? Any idea which future release of S/4 will have this functionality out of the box?
Sasha
User | Count |
---|---|
94 | |
8 | |
6 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.