Project Systems - BAdI ME_COMMTMNT_PO_REL_C was activated and commitment is not working

Former Member
0 Kudos

Hello All:

We are implementing PS and we found out that there is a BAdI we can activate in order to change the way Purchases Orders affect the Commitment calculations.

We activated it and implement the changes on the ABAP to increase commitment only when PO is released. The implementation works, but only for the Projects generated before the activation, for the new Projects generated after the activation no AC Commitment Documents were generated; therefore, Commitment is not being controlled.

We have applied several notes regarding not Commitment generating but we have not made it work.

Can anyone help us on this?

Thank you very much.

View Entire Topic
Former Member
0 Kudos

Thank you very much for all your help, all were very helpful specially when saying that we are trying to make change during creation.

I will put the exact solution as soon as I documented.

Regards,

former_member211458
Participant
0 Kudos

Hola cesar,

Justo Estoy tratando de implementar la badi para que solo comprometa presupuesto cuando se libere la orden de compra. Podrias indicarme los pasos de como lo hiciste ?

Saludos