Project Systems - BAdI ME_COMMTMNT_PO_REL_C was activated and commitment is not working

Former Member
0 Kudos

Hello All:

We are implementing PS and we found out that there is a BAdI we can activate in order to change the way Purchases Orders affect the Commitment calculations.

We activated it and implement the changes on the ABAP to increase commitment only when PO is released. The implementation works, but only for the Projects generated before the activation, for the new Projects generated after the activation no AC Commitment Documents were generated; therefore, Commitment is not being controlled.

We have applied several notes regarding not Commitment generating but we have not made it work.

Can anyone help us on this?

Thank you very much.

View Entire Topic
kenmelching
Active Contributor
0 Kudos

You need to debug your BADI to find where the error is occurring.  I have encountered similar situation where you are implementing a user exit to change something (a WBS for example) but you are trying to make the change during creation.  You cannot change an object during creation because it doesn't exist yet.  There are ways to do it but it takes a good ABAPer.

Are you trying to change a Commitment Document before it has been saved?