Project stock (WBS element) not consider in QA07 Transaction

Former Member
0 Kudos

Standard SAP transaction QA07 for Deadline monitoring of batches not

considering project stock (WBS element) for the same

Kindly suggest for your possible solutions as we are going to fully equipped with

project system and its stock must be

considered for background scheduler of recurring inspection

Waiting for your kind and immediate action

With Regards,

Kunal Sheth

Accepted Solutions (0)

Answers (1)

Answers (1)

erika_szanto
Active Participant
0 Kudos

Hi!

We regret to inform you, that the report RQAAAS10 ( QA07 ) does not

support project stocks.

For better understanding of the transaction QA07, I would ask you kindly

to review the documentation for the report RQAAAS10.

Here are the Requirements for this report:

'The batch master data corresponds to the selection conditions.

Only those batches that full fill the following conditions are examined:

-the batch status is "released".

-the unrestricted-use stock is greater than zero.

-the stock is not in a HU storage location'

This means that all 'special' stock locations, like for example project

stock, will be not relevant for this transaction.

Unfortunately SAP not able to provide a workaround for your

issue, with the exception of a customer own development. In this case

you can copy the report and make the correspondent adjustments needed.

Best regards

Erika