Dear Experts,

For on going project, we want to recognize the revenue based on the percentage of completion. Final bill will be at the end of the project, how to recognize the revenue in Finance on unbilled items/completion.

Please let me know what are the config setting to be done and steps to be executed (SD/PS/CO Module) for this process.

Regards,

vgl

Accepted Solutions (0)

Answers (1)

Answers (1)

ravichandran_iyer
Active Contributor
0 Kudos

You'll have to implement Result Analysis in CO. This does exactly what you require. You can take a look at the following links which will guide you through. Also, there are numerous other resources available in the internet.

http://wiki.sdn.sap.com/wiki/display/ERPFI/UnderstandingResultsAnalysisforWIP

http://wiki.sdn.sap.com/wiki/display/BI/MaintainingResultsAnalysis+Keys

Ravi.

Former Member
0 Kudos

Issue resolved