on 2018 Jul 19 7:34 PM
Hello experts,
I am by far not an SAP expert and I have a problem. I am looking at CJ30 and there is a column for budget which looks like the original budget amount, the current budget which is more than the original and distributed/distributable which mirror the current budget amounts.
How can I get the current budget back to the original budget numbers. The previous person altered the originals when they should not have been.
Thanks for any help you can provide.
Run CJ37 which are Budget Supplements which are added to the Original Budget. Delete them if necessary.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
10 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.