Project Budget question

Former Member
0 Kudos
205

Hello experts,

I am by far not an SAP expert and I have a problem. I am looking at CJ30 and there is a column for budget which looks like the original budget amount, the current budget which is more than the original and distributed/distributable which mirror the current budget amounts.

How can I get the current budget back to the original budget numbers. The previous person altered the originals when they should not have been.

Thanks for any help you can provide.

kenmelching
Active Contributor
0 Kudos

Please submit a new question with more details and screenshots.

Accepted Solutions (1)

Accepted Solutions (1)

kenmelching
Active Contributor

Run CJ37 which are Budget Supplements which are added to the Original Budget. Delete them if necessary.

Former Member
0 Kudos

Thank you Ken,

This looks like it wants to work but now I'm getting now that the "item WBS element xxxxxxx budget exceeded" so the changes worn't save. Is there an override to this?

Thanks,