How we can transfer the cost booked on 1 WBS element on profit centre A (Say) to the same WBS element on profit Centre B (Say) ?

Any transaction ?

Regards

Ashish

Accepted Solutions (1)

Accepted Solutions (1)

iklovski
Active Contributor
0 Kudos

Hi,

Profit centre is derived from the master data of WBS. So, it cannot be two PCtrs at the same time. For the transfer between profit centres you can use 9KE0 transaction.

Regards,

Eli

Former Member
0 Kudos

thanks

Former Member
0 Kudos

Thanks