4 weeks ago
Hi,
I'm trying to convert Planned order to Production order, I get the error " Production version required - Planned order 844 will not be converted Message No. 40432". But I do have a Valid Production version maintained for this material that's within the validity of Planned order dates. The BOM and Routing status is active, the dates are within the planned dates, the individual/collec indicator in MRP 4 view was blank, I tried all three options, blank, 1 and 2 but same error.
MD04 exception message = 52 (No Bom Selected)
Could you please help me resolve this?
Yep that's it ! 😅
I might just be the stupidest person alive today.
Thank you for your answer, I corrected the date and now I have the Prod order.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
8 | |
6 | |
5 | |
5 | |
5 | |
5 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.